CPM and PERT MCQ'S
1. The numbering of the nodes in A-O-A is done A.From left to right B.From Right to Left C.Randomly D.On the basis of the duration of the activity 2.Which of the following is not the part of Risk Control A.Execution of the risk response strategy B.Monitoring of triggering events C.Initiating contingency plans D.Not watching for new risks 3. Conflict occurrence in projects is A.Unavoidable B.Depend on type of project C.Avoidable D.Depends on culture 4. Outsourced projects are susceptible to conflicts as A.People get less pay in these projects and work is more B.More work pressure and less time horizon C.These projects are away from home location D.People are unaccustomed to working together and have different values 5. Who creates the project team? A. Factory manager B. Operation manager C. Project manager D.Purchase Manager 6. Project Manager must ensure that it develops appropriate trade off/s as A. Time, cost and performance B. Time, value and performance C.Men...